Guide

The San Francisco
ADU permit process

How the San Francisco ADU permit process works — design, engineering, planning and code review, building permit, structural and MEP inspections, and final sign-off.

An ADU permit runs through design, structural engineering, planning and code review where applicable, building permit submission, a review and correction loop, then permit issue. During construction, work holds for foundation, framing and MEP inspections before anything is covered, and finishes with a final inspection.

Important

This page describes process, not current code

Requirements change. This guide explains the shape of the process — what happens, in what order, and who is responsible at each stage — rather than stating specific current code requirements, which should be confirmed with the City and with your design team at the time you apply.

Leafair is a licensed general contractor. It coordinates the permit and the inspection holds during construction. It does not produce the drawings or the structural calculations, and it does not interpret code on your behalf.

Process

The permit process, stage by stage

StageWhat happens
DesignArchitect produces drawings that satisfy the layout, the site constraints and the applicable requirements.
Structural engineeringEngineer produces stamped drawings and calculations for anything carrying load.
Planning and code reviewWhere applicable, the proposal is reviewed against planning and zoning requirements before or alongside the building permit.
Building permit applicationThe full drawing set is submitted for review.
Review and correctionsComments come back, the design team responds, and the set is resubmitted as needed. This loop is normal.
Permit issuedConstruction can begin. Not before.
Structural inspectionsFoundation reinforcement is inspected before concrete is poured. Framing is inspected before it is covered.
MEP inspectionsPlumbing, electrical and mechanical rough-in inspected while still open.
Insulation and coverOnly after rough-in has passed.
Final inspectionThe completed unit is inspected and signed off.
What to ask

What should I ask before applying?

Who submits the application and who responds to review comments. Whether engineering is included in the design fee or separate. What happens to the construction schedule if review runs long. Who calls the inspections during construction, and what the process is when something fails.

Next

Related reading

How to build an ADU in San Francisco and what drives ADU cost. To discuss a property, see ADU construction with Leafair.

Questions

Common questions

Do I need a permit to build an ADU?

Yes. An ADU is a new dwelling unit and is permitted, reviewed and inspected work. Anyone offering to build one without a permit is offering you a problem at resale.

How long does permit review take?

It varies and it is outside a contractor's control. Treat it as a genuine schedule item. Nothing should be ordered or trades booked on the assumption that review will be quick.

What happens during construction inspections?

Work stops at defined points so an inspector can see what is about to be covered — typically foundation reinforcement before the pour, and framing and MEP rough-in before insulation and drywall. Work that gets covered before sign-off may have to be opened again.